Solvacom Maintenance - Migration of cluster

Scheduled Maintenance Report for protel Cloud Center

Completed

The scheduled maintenance has been completed.
Posted Aug 10, 2025 - 04:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 10, 2025 - 02:00 CEST

Update

We will be undergoing scheduled maintenance during this time.
Posted Aug 07, 2025 - 16:15 CEST

Scheduled

Customers in France whose system is hosted by Solvacom will experience scheduled maintenance between 2:00 AM and 4:00 AM (local time). You have also been informed via email with the exact maintenance dates.

During this time, access to protel may be temporarily unavailable.
If any issues persist after the maintenance window, please contact your support team.

Please perform your End of Day before the maintenance window.

Purpose of Change:
The objective is to migrate VMs currently hosted on a Nutanix cluster with G5 and G6 nodes
to a new G9 cluster to ensure infrastructure modernization, performance improvement, and
long-term supportability.
Posted Aug 07, 2025 - 15:53 CEST
This scheduled maintenance affected: protel OnPremise (protel OnPrem (SPE/MPE)).